Nvidia launches DSX POD modular data centre reference design

What happened

AI digest

On 21 October 2026, Nvidia launched DSX POD at GTC Berlin, a modular data centre reference design built around Vera Rubin systems. Partners including Dell, HPE, Lenovo and Schneider Electric complete the installation and testing of compute, networking, cabling, power and liquid cooling in the factory, so on-site work is limited to connecting power, cooling and network. Nvidia says the approach can cut deployment time from six months to as little as 14 days.

Written by AI from the reports · updated 2 h ago

Timeline

Follow the reports to see the event from each side.

Oct 21
  1. The Decoder
    Nvidia's DSX POD could cut AI data center setup from six months to as little as 14 days

    Nvidia wants AI data centers to ship fully preassembled in containers.

Heat of this event